March 10, 2020

Schedule ProgressArea / Phase Description of Phase Projected Phase Completion

Phase 1 New Two-Story Addition 65% Complete In Progress – Phased Summer 2020

Phase 2 Administration / Entrance 75% Complete In Progress – May 1, 2020

Phase 3A Nurses Area 75% Complete In Progress – May 1, 2020

Phase 3B Family Consumer Science Completed – August 28, 2019

Phase 4A Mechanical Room Not Yet Started – July 1, 2021

Phase 4B Band Not Yet Started – May 1, 2021

Phase 5A Renovations Two-Story Classrooms Not Yet Started – July 3, 2021

Phase 5B Renovations Two-Story Stairs & Core Not Yet Started – December 1, 2020

Phase 6 New Cafeteria & Classrooms Not Yet Started – January 2, 2021

Phase 7 Renovate Cafeteria Not Yet Started – September 1, 2020

Phase 8 New Auxiliary Gym 25% Complete In Progress – September 15, 2020

Phase 9 Locker Rooms Not Yet Started – August 1, 2021

Phase 10 Renovation Classrooms G Not Yet Started – May 1, 2021

Phase 11 Renovations to Pool Area Not Yet Started – August 1, 2021

Phase 12 Renovation Existing Gym Not Yet Started – August 1, 2021

Project Considerations

Maintaining Schedule – The project team is working to maintain the progress

in the new classroom wing and planning is underway for the summer cleaning

and move-in

Reducing Costs – The project team is working to find ways continue to reduce

costs and provide options for scope reduction/cost reduction

Maintaining Utilities – The project team continues to work to keep all utilities

in operation throughout the building during the construction; this will be an

ongoing effort for the remainder of the project.