40 Avenue NE Bridge Replacement...In the interim, traffic will need to use the Snell Isle Boulevard...

Post on 05-Oct-2020

0 views 0 download

Transcript of 40 Avenue NE Bridge Replacement...In the interim, traffic will need to use the Snell Isle Boulevard...

40th Avenue NE Bridge Replacement

http://www.40thavenuebridge.com/

Engineering & Capital Improvements

Project Number: 18032-110

Summary of Events

03/15/18 City Council approval of:

Acknowledgment of the selection of Cardno, Inc. as the most qualified firm

Authorization of preliminary services

Website Development Completed

Temporary Traffic Flow Recommendations In Process of implementation

Pedestrian Accessibility In Design

Project Website Completed 05/22/18

http://www.40thavenuebridge.com/

Temporary Traffic Flow RecommendationsIn process of implementation (Completion on 06/06/18)

Pedestrian AccessibilityIn Design

Develop design which allows pedestrian and bicycle access:

Coordinate with contractors for constructability

Provide improvements which can be incorporated during the Maintenance of Traffic

Can be maintained during construction to provide continuous access to residents

Requested Approval

Authorization of the First Amendment to the Agreement

Public involvement,

Geotechnical engineering services,

Topographic survey,

Bridge Hydraulics Report,

Bridge Development Report,

Necessary Services for compliance with National Environmental Policy Act (NEPA).

40th Avenue NE Bridge Replacement