24 Road (Lake Cushman) Reconstruction Project

Interagency partnership and funding

Funding

• Total project funds available:

~ $4.6 million

• Funding sources: • Federal Lands Transportation

Program • Tacoma Power • US Forest Service • National Park Service

24 Road (Lake Cushman)

Project goals:

• Meet FERC requirements • Permanent dust abatement • Improved road surface • Reduced traffic congestion • Safety features • Improve Olympic NP utility

infrastructure

Project scope

It’s happening…!

•February 2020: Engineering design finalized

~ Contract and award ~

•Summer 2020 (July – Sept): Road closure / construction

Date: May 2019 Subject: Utility Installation ONP

Separate phase, pending future funding: Bear Gulch

(Storm Damage – 2017)