STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 23.03.13

1.Basement-II Slab Completed.2. Basement-I slab flat no 1 & 2 completed reaming slab planning today

3.Ground Floor slab Flat No 01 & 02 Shuttering Completed

STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 23.03.13

1.Basement-II Slab Completed.2.Basement-I Slab completed

3.Ground floor slab flat no 1 & 2 completed4.First Floor flat no 01 & 02 Shuttering In Progress

STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 23.03.13

1.Basement II Slab Completed.2.Basement I flat no 01 Completed

3.Basement I flat no 02 Beam Bottom Shuttering work in progress

STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 23.03.13

1.Basement II Slab Completed.2.Basement I Slab Completed

3.Ground Floor flat no 1 & 02 Shuttering Completed

STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 23.03.13

1.Basement II Slab Completed2. Basement I slab for flat 1 &2 completed

3.Remains Slab Beam Bottom Shuttering Work In Progress

STATUS REPORT OF MY HOME ABHRA “CENTRAL LAWN”As On 23.03.13

1.Grade Slab- (Out Of 3-Parts) 1 Part Completed2.Sand Leveling Work in Progress

STATUS REPORT OF MY HOME ABHRA “TOTAL SITE”As On 23.03.13

1.Total Site Basement II slab- Completed2.Total site Basement I Slab (Except Tower-C 1flat and Tower-E 3 Flats)-Remaining

Completed3.Ground Floor slab Tower B 1&2 flats completed

SWIMMING POOL