Challenges of Olympic Proportions: An Analysis of Project Management
Techniques to Overcome Challenges of Mega Events
Adam Newton
Pennsylvania State University
Table of Contents
1.0 Background 3
2.0 Statement and Evidence of the Problem 4
3.0 Defining the Challenges of the Mega Event 7
3.1 Organizational Requirements 8
3.2 Monument Complex 10
3.3 Urban Renewal 13
3.4 Sustainability 15
3.5 Human Rights 17
4.0 Overcoming Challenges of the Mega Event 19
4.1 Assess 22
4.2 Allocate 25
4.3 Adapt 33
4.4 Aftermath 37
Bibliography 41
2
Background
Global mega events like the FIFA World Cup, the Olympic Games and the
World Expo have grown in popularity, size, scale and cost over the past few
decades thanks to the ever-increasing impact of globalization. These “urban
occasion[s] of multidimensional global significance” (Deng & Poon, 2013, p. 23)
provide countries across the world with opportunities to create a lasting
impression on audiences through the use of massive-scale spectacles that
require years of advanced planning to put necessary infrastructure, logistics and
support teams in place all while meeting stringent requirements for post-event
sustainability. Such planning addresses a combination of factors that lie internal
(e.g., event size, scope, timeline, etc.) and external (e.g., event visibility,
environmental impact, impact on tourism) to the core event itself (Gauthier,
2013).
While there are many large events, whose scale is by no means small,
few reach a magnitude to be considered “mega.” For the purpose of this paper
we will define a mega event based on the following criteria: multi-billion dollar
budgets, more than 5 years of planning, required infrastructure development and
has a multi-national impact (Flyvbjerg, 2014, p. 6). To further constrain this
analysis, we will only focus on the Olympic Games and the FIFA World Cup as
the prominent mega events to be studied as they provide the strongest examples
of the colossal effort and subsequent impact involved in the production of
modern-day global mega events. As Gauthier (2013, p. 60) states, the Olympic
Games “[are] not restricted to the athletic tournament, but also involves cities that
3
fiercely compete to host ‘the greatest show on earth.’” For instance, the Olympics
and other mega events are seen as a catalyst for rejuvenating the host city or
country’s infrastructure, building patriotism among citizens and stimulating the
economy to support an influx of tourism, media and sponsorship in years to come
(Gauthier, 2013).
Statement and Evidence of the Problem
Mega events bring about many of the same political, social and economic
issues as mega projects, yet mega events also must deal with the unique
challenge of occurring on a global stage that will magnify failures just as much as
successes (Jennings & Lodge, 2011; Grabher & Theil, 2014). The high
expectations and subsequent risk of large-scale failure inherent to hosting mega
events is especially dangerous for localities with developing economies such as
the BRICS, Argentina and Qatar, all of which increasingly vie for the privilege of
hosting mega events since China secured the Summer Olympics in 2008 (Junior,
2014). It has begun to be argued that the best way to protect such fledgling hosts
from the potential negative side effects of their undertaking is to take a proactive
approach to understanding, identifying and diagnosing in advance the common
mega event challenges rather than waiting to treat the symptoms of failure once
they have already appeared by using traditional project management responses.
Looking at the history of the mega event, enormous (yet avoidable) cost
overruns are the most common failure. For example, initial cost estimates for the
4
London Olympics placed the total cost at £1.8, yet the ‘final’ cost totaled £9.3
billion excluding items not considered to be within the official budget. (Jennings &
Lodge, 2011) Similarly, experts estimate that the 2014 Winter Olympics in Sochi,
Russia reached a record $51 billion in expenditures despite the fact that Winter
Olympic Games typically cost far less than their summer counterparts. This
overage is due at least in part to the notably absurd $7.8 billion spent to connect
two competition locations in Russia, which, as a point of reference, is more than
NASA spent to send the Curiosity rover to Mars. In fact, the costs for the road
were so astronomical that the Russian version of Esquire estimated that the
same road “could have been covered in an eight-inch layer of foie gras for the
same price” (Arnold & Foxall, 2014, p. 6).
That said, not all mega events are doomed and some, like the 1984
Olympics, even manage to produce multiple positive outcomes. Hosted in Los
Angeles, history can trace the 1984 Olympic Games with bringing about
significant economic, infrastructural and social revitalization within the city, a feat
that set the bar high for all Olympics that followed. Unfortunately, as Table 1
illustrates, replicating the success seen in 1984 has been next to impossible
thanks to, in part, the increased size, scale and cost of the Games that have
occurred since then (olympic.org).
5
Games Nations Athletes Sports Events1984 140 6797 23 2211988 159 8465 25 2371992 169 9367 28 2571996 197 10,320 26 2712000 199 10,651 28 3002004 201 10,625 28 3012008 205 10,942 28 3022012 204 10,568 26 302
Table 1 (olympic.org)
Initial research suggests that many mega events fail because of a skewed
cost-benefit analyses, a lack of “honest” numbers and a general lack of rigor in
the initial planning stages of mega events, which ultimately lead planning
committees to approve projects that have otherwise clear negative economic,
social and environmental consequences (Jennings & Lodge, 2011). Aspirational
mega event hosts often allow their optimism to override logic and, in the process,
underestimate or even overlook the major risks involved. For example, many
misguided hosts dangerously assume that investing in a mega event will
generate enough income to offset the upfront costs, but history proves otherwise.
Next, hopeful hosts commonly justify the massive and often unrecovered
costs involved in mega events by incorrectly pointing out that the infrastructure
developed for the event will benefit their community for years to come. In reality,
however, most mega event infrastructure is nearly useless following the initial
event due to the rushed, construction that accompanies impossibly short
timelines or the unsustainably high maintenance fees and capacities that are
required to keep the facility in use indefinitely. Finally, many hosts do not see
6
legacy as a risk, yet it is easy for the poor reputation that follows a less-than-ideal
event to remain a curse long after the event’s conclusion.
To avoid such judgment errors, it is critical that all potential hosts carefully
evaluate all mega event outcomes—positive and negative; short-term and long-
term—before beginning the bidding process. Upon deciding to move ahead, the
host should take inventory of all of the common challenges that plague mega
events and set actionable measures for minimizing and/or avoiding the
challenges altogether. Based on the limited literature on the topic, such
challenges fall within the following five categories, all of which we will fully
explore:
• Organizational Requirements
• Monument Complexes
• Urban Renewal
• Sustainability
• Human Rights
Defining the Challenges
Often the symptoms of a mega event’s shortcomings are identified as, for
example, grossly over-budget or a negative public image, but to address these
issues we must first understand their causes. After reviewing various outcomes
of past mega events, we suggest that these challenges are, individually or in
combination, root causes of these symptoms. By identifying them, we are able to
understand how they come about and what measures can be taken to avoid
7
them and their negative outcomes. We will discuss each in detail, providing
examples of how they have historically occurred, then transition into proposed
recommendations to mitigate or avoid these challenges in the future.
Organizational Requirements
The complex organizational structure and stringent organizational
requirements that accompany most mega events are the first hurdle to identify,
plan for and avoid. A mega event acts as a loosely formed organization that
holds “a compound rather than a mixture of objectives” (Deng & Poon, 2011, p.
28). Each mega event will have a governing body or parent organization that sets
standards for maintaining a cohesive experience from event to event. The parent
organization holds each host to stringent standards that must be met, no matter
how lucrative or exaggerated. The classic example of such a body is the
International Olympic Committee (IOC), which consists of 125 members
representing a spectrum of countries that oversee the Games (Malfas &
Theodoraki, 2004). The IOC sets legal requirements that all hosts must meet
before even submitting a bid, stating that all Olympics bidders “must protect
Olympic word marks, promulgate anti-ambush marketing laws, ensure entrance
to the country for members of the ‘Olympic Family,’ and a governmental
guarantee of any fiscal shortfall” (Deng & Poon, 2013, p. 50, with emphasis
added).
8
Moving down the chain of command, regional committees and local
governmental agencies, though disparate, are ultimately charged with
implementing the requirements of the parent organization and making the mega
event come to life in conjunction with the organization’s wishes. As Deng and
Poon (2011, p. 27) write,
“Due to these unconventional complexities, mega events are often
realized through cross-boundary collaboration efforts. They can be jointly
promoted by several government agencies, developed by multiple
business entities and delivered by interdisciplinary consultants from
multiple design and construction practices.”
Because of this complex structure, it is an inevitability that conflicts in
priorities, communication channels and negotiations will take place between the
various parties involved in carrying out a mega event. Cross-organizational
synergy is necessary for producing a successful event, yet the boundaries that
exist between organizations often block information flow and prevent resource
sharing, dooming any hopes of clear and succinct collaboration (Deng & Poon,
2011).
For instance, Brazil enacted a law in 2003 that “effectively prohibited
alcohol sales at stadiums during football matches” (Gauthier, 2013, p. 58), but
then later won a bid to host the 2014 FIFA World Cup. Upon visiting Brazil, the
9
Secretary General of FIFA, Jerome Valcke, expressed the organization’s
discontent with the alcohol ban, stating that “alcoholic drinks are part of the FIFA
World Cup, so we’re going to have them” and essentially forcing Brazil to allow
the consumption of alcohol or risk losing the right to host. It is speculated that the
official beer sponsor of the World Cup aided Valcke in winning his battle against
Brazil, as the sponsor had previously paid tens of millions of dollars in securing
exclusive pouring rights at the games (Junior, 2014).
The collaboration of FIFA’s Secretary General with the official beer
sponsor perfectly illustrates a common yet unethical crutch that mega events use
to circumvent the inevitable intra-organizational conflict inherent in mega events:
political alliances. Many mega events, especially mega sporting events,
commonly engage corporate elites and local politicians in profitable partnerships
aimed at furthering the goals of the parent organization. The practices of such
alliances, termed “politics of place,” typically involve campaigns to convince the
government or citizens of the host city to cough up additional tax money for use
in the event, even though it is those same taxpayers that end up footing the bill
when the event does not profit. (Gauthier, 2013).
Monument Complex
In addition to organizational requirements and political nuances, mega
event planning committees often fall victim to what is known as a “monument
complex” or “a desire to leave lasting monuments to their vision, world view and
10
time in office” (Jennings, 2013, p. 6). Simply put, monument complexes come
into play when planning committees unnecessarily complicate the tasks at hand
with overly ambitious architecture designs and impractically costly construction
and technology implementations just for the sake of legacy, whether their own or,
more often, that of a key event influencer (e.g., politicians, top businessmen, etc.)
(Jennings & Lodge, 2011).
Planning committees’ inability to appropriately forecast and manage risk
often magnifies the negative impact of monument complexes. For instance,
planning committees suffering from such a complex will shortsightedly
underestimate risk, especially financial, and overestimate benefits to gain
necessary approvals when bidding and planning for a mega event project. Doing
so leads the final cost of the event to far exceed projections while the benefits fall
short, which ironically takes a significant toll on the legacy of the event that that
planning committee worked so hard to produce (Jennings & Lodge, 2011).
History suggests that two of the most recent Olympic Games (London
2012 and Sochi 2014) both fell victim to the monument complex hurdle. It can be
seen as a central issue of the 2012 London Summer Olympics, on the heels of
the notoriously costly Millennium Dome, a project that concerned then Prime
Minister Tony Blair greatly:
11
“When the [Olympic] bid was first raised as a possibility, most of the
cabinet were dubious and the Treasury was hostile... after the Dome, we
were all a trifle nervous of anything so immense, costly and liable to turn
out tricky. [Blair] was attracted to the bid because he liked the boldness of
the notion,” persuaded by the cajoling of Culture Secretary Tessa Jowell
who, he recollected, “looked at me reproachfully and said, ‘I really didn’t
think that was your attitude to leadership. I thought you were prepared to
take a risk. And it is a big risk. Of course we may not win but at least we
will have had the courage to try’” (Jennings, 2013, p. 5).
Similarly, Russian President Vladimir Putin made the 2014 Winter
Olympics in Sochi his pet project, so much so that he began holding state
receptions at his summer residence in Sochi while proclaiming his goal of
developing the city into a world-class winter resort (Jennings & Lodge, 2011).
Putin was not alone in his optimism, as many outside observers truly believed the
Games would lay the groundwork for Russia’s reemergence as a great
geopolitical and geo-economic power, as “only first-rate powers are awarded
such prestigious events, goes the reasoning, ergo Russia is a first-rate power”
(Arnold & Foxall, 2014, p. 6).
Unfortunately, Putin and the Games’ organizers let their intentions get the
best of them and, not surprisingly, encouraged huge cost overruns that ultimately
12
only served to solidify Russia’s poor reputation on a global stage rather than
remedy it.
Many mega event organizers and planning committees blow their budgets
seeking dramatic impact without realizing that any impact gained will likely be
short-lived at best. A study of the tourism implications of the Olympic Games
found that the Games’ overall effect on tourism was, in fact, negative (Malfas &
Theodoraki, 2004). For example, the study concluded that the 1988 Summer
Olympics in Seoul and the 2004 Summer Olympics in Athens did not have a
long-term, positive impact on local tourism (Malfas & Theodoraki, 2004).
Urban Renewal
No city is completely equipped to deal with the organizational and political
demands and sheer population influx that go along with hosting a mega event,
though some have a much better head start than others. In preparation, many
host cities will be pressured to spend millions or billions on infrastructure in
preparation for the event, with the justification for said spending being that the
project will help with future urban renewal. In advance of hosting the 2014 Winter
Games, Sochi, Russia “did not have a single sports venue… and as a result,
roughly 85 percent of stadia infrastructure for the Games [was] been built from
scratch” (Arnold & Foxall, 2014, p. 7).
13
With a mega event comes an influx of tourists, volunteers and media that
need housing, impact city flow and traffic patterns and increase food
consumption and waste disposal. Prior to the arrival of these crowds, the
construction of housing and new roads and the development of public transport
to/from the event venues are required. Most planning committees do not stop
here, however, instead using the event as an excuse to engage in massive
infrastructural development that is not directly related to the event, all under the
guise of improving the physical appearance or functionality of the host city or
region. As one author notes, “[M]ega events [are] one of the main products of
post-modern society and a key means by which cities express their personality,
enhance their status and advertise their position on the global stage” (Malfas &
Theodoraki, 2004, p. 211).
Inflated infrastructure spending haunted the 1976 Summer Olympics in
Montreal, which included the construction of a stadium playfully named the “Big
O” because of its doughnut-shaped roof. Later, once the stadium’s true cost
came to light, citizens branded it with an alternate version of its original name:
the “Big Owe.” Thanks to the stadium and other similar missteps, it took Montreal
three decades to pay off the cost of hosting the Games (Deng, 2012). To add
insult to injury, the planning committee lacked the foresight to make the design of
the “Big O” match its surroundings, which ultimately kept Montreal from being
able to repurpose the stadium as a sports park in an effort to rebrand Montreal as
a sports destination city (Deng, 2012).
14
In addition to costs, timeline pressures often lead planning committees to
disregard future use in favor of making sure that all construction projects are
ready on deadline. Furthermore, timelines are often used by politicians and other
power players to create a sense of urgency that they can use to bypass the
standard procedure for urban development application approvals, including
public hearings, environmental surveying, social assessments and the like
(Gauthier, 2013). This need for completion at any cost contributed to the multiple
failures of the 2014 Sochi Winter Olympics, specifically the road development.
Many roads in Sochi, including the aforementioned multibillion-dollar “foie gras
road,” were poorly constructed, riddled with potholes, or simply left unfinished
(Junior, 2014).
All host cities must update infrastructure in some manner, whether on a
large or small scale, to support the temporary increase in population associated
with mega events. Knowing this, planning committees should take great care to
assure each project has a vision and strategy for the short-term as well as the
long-term and not take quick out-of-scope shortcuts in the face of political or
deadline pressures. As seen in the example of the 1984 Los Angeles Olympics,
being wary of scope creep and enhancing existing structures instead of building
new structures from scratch can ensure that events end with a new profit, not
long-term debt in the form of infrastructure.
15
Sustainability
Grandiose sustainability plans often go unfulfilled after a mega event,
largely because organizers’ lack of long-term vision leads them to prioritize the
immediate steps needed to make the event happen over figuring out how to have
the greatest possible impact in the long run (Deng & Poon, 2011). In addition,
capacity and building requirements often morph well-intentioned infrastructure
initiatives into behemoth projects that stand little chance of finding a frequent use
after the mega event, resulting in heightened cost overruns (Deng, 2012). For
instance, the average seating capacity of the five Olympic stadiums built since
2000 comes to 89,147, which is vastly greater than the typical demand for
conventional tourist and sports facilities. In fact, crowds that large may not occur
again for decades, if at all, which explains why the Olympic stadiums in Montreal,
Sydney and Athens have been largely underused after the Games (Deng, 2012).
The Vancouver Olympic Village is an ideal example of the challenges
found in the tension between building requirements, costs and overzealous
future-use promises. Organizers originally proposed the Village as a LEED
Platinum-rated, zero-net energy efficient community that would convert raw
sewage to heat the buildings. In addition, the Village was to be a cultural and
residential destination that included sites for urban agriculture among other
amenities. Despite the best of intentions, the Village ultimately failed to succeed
due to projected costs of living higher than those seen in luxurious, high-rise
Manhattan rentals. In the end, when the Games ended and the Village went
16
unoccupied, the city of Vancouver and its taxpayers were left with the $1 billion
bill, making the Village one of the biggest financial losses that the city ever
experienced (McCarthy, 2012).
In addition to future-use options, planning committees should also take
into consideration the impact that the mega event will have on those currently
living on the event site, who could face rapid gentrification and eventually
eviction. The 1996 Atlanta Games are a cautionary tale of such negative social
impacts. In preparation for the Games, the city demolished multiple public
housing projects, which left approximately 15,000 residents homeless. As Malfas
and Theodoraki (2004, p. 213) report, “9500 units of affordable housing were lost
and $350 million in public funds was diverted from low-income housing, social
services and other support services for homeless and poor people to Olympic
preparation during the same period.”
Human Rights
The perceptions and opinions of the general public are one final hurdle of
the mega event to be avoided. In addition to the homelessness that follows
gentrification, the 24-hour news cycle and ever increased interconnectedness of
the world make all aspects of a mega event—whether positive or negative, public
or private—more visible to the general public than ever before. While it is nearly
impossible to not offend or upset anyone at all when working on a massive scale,
angering or alienating a sizeable portion of the population, locally or afar, stands
17
to cause significant problems for the climate, attendance and general public
support of the event.
For instance, the 2014 Sochi Winter Olympic Games, among its many
issues, suffered from a public image problem. Typically, governing organizations
like the IOC try to avoid controversial political or social issues, but the timing of
Russian President Putin’s June 2013 signing of a law against “nontraditional
sexual relationships” made avoiding controversy impossible for the upcoming
Winter Games (Arnold & Foxall, 2014, p. 4). Multiple LGBT and human rights
organizations called for a boycott of the Olympics in advance, but boycott did not
occur. As a result, the offended global public took great pride in celebrating
Sochi’s failures, including its failed final ring opening during the opening
ceremonies. All signs suggest that Russia’s discriminatory take on human rights
—and not the performance or scenery of the Games—will ultimately go down in
history as Sochi’s legacy.
Russia is not the lone offender when it comes to human rights issues,
however. Gentrification and resultant displacement similar to that of the 1996
Atlanta Olympic Games has also occurred as part of the 2012 London Summer
Olympics and the recent 2014 World Cup in Rio, Brazil and there are reports that
“a man who was evicted to make way for the 1968 Summer Olympics is set to be
evicted for the 2020 Tokyo Olympics” (Junior, 2014). Still worse, it has been
reported that at least 1,200 migrant workers have died in Qatar in recent years,
18
with the number expecting to reach 4,000 by the 2022 World Cup – though the
Qatar government denies there is any relation between the deaths and stadium
construction (Ingraham, 2015). Additionally, Qatar’s kafala rules for employment
prevent employees from unionizing, forcing the Secretary General of the
Supreme Committee for Qatar 2022 to publicly address labor concerns. As the
Secretary General stated, “We admit that there are labor issues here in the
country, but Qatar is committed for reform. We will require that contractors
impose a clause to ensure that international labor standards are met” (Gauthier,
2013, p. 68).
The above examples expose the humanitarian issues inherent in the
staging of many mega events but do not address another common concern: the
use of public money. Controversy abounds in mega event financing, as seen in
Boston declining to put forth a 2024 Olympic bid, with many taxpayers not
approving of local and state governments’ decisions to allocate funds toward
mega events—funds that could be used for projects for the public good
(Gauthier, 2013).
Overcoming Challenges
As we have discussed thus far, there is a reoccurring instance of mega
event organizers stumbling over challenges by ignoring cautionary tales and
thereby becoming victims to the “pricing forgetfulness” that will ultimately doom
them to suffer the same fate of previous planners (Deng, 2012). In this section,
19
we will explore traditional project management practices that focus on mega
projects and adapt those recommendations into the management of mega
events.
For context, mega projects, as defined by Miller and Lessard,
“are high-stakes games characterized by substantial irreversible
commitments, skewed reward structures in case of success, and high
probabilities of failure. Once built, projects have little use beyond the
original intended purpose. Potential returns can be good but they are often
truncated. The journey to the period of revenue generation takes 10 years
on average. Substantial front-end expenditures prior to committing large
capital costs have to be carried. During the ramp-up period, market
estimates are tested and the true worth of the project appears; sponsors
may find that it is much lower than expected. (Miller and Lessard, 2001, p.
437.)”
And further clarified by Flyvbjerg as: “large-scale, complex ventures that
typically cost US$1 billion or more, take many years to develop and build, involve
multiple public and private stakeholders, are transformational, and impact
millions of people (Flyvbjerg, 2014, p.6).”
Within the traditional project management field, cost overruns have been
recorded and an accepted outcome for nearly 70 years. Flyvbjerg presents the
20
“Iron Law of Mega projects, suggesting that nine out of ten such projects have
cost over- runs; overruns of up to 50% in real terms are common, over 50% are
not uncommon.” Such examples range from the Suez Canal (1,900% cost
overrun), the Sydney Opera house (1,400% overrun) and Denver International
Airport (200% cost overrun). Though in the past decade, front-end planning has
been touted as the counterapproach to lessen these overruns and align the
project (Flyvbjerg, 2014 p. 9-11). For context, a selection of mega project costs
have been provided in Table 2. With these definitions and historical benchmarks,
we can begin to note correlations between mega projects and mega events (e.g.:
lengthy timeline and large capital costs).
Joint
Strik
e Figh
ter
China H
SR
Intern
ation
al Spa
ce S
tation
Sochi
2014
Lond
on's
Cross R
ail
UK NHS IT
Athen's
Olym
pics
050
100150200250300350400450 400
300
150
51
26 18.3 11.5
Mega Project Costs (billions $)
Table 2 (Flyvbjerg, 2014 p. 9)
21
For the purpose of comparison, we will equate the previously presented
challenges to the multi-dimensional risks in mega projects discussed by Miller
and Lessard and adapt from their process to cope with risks for a structure to
avoid or lessen the impact of challenges for this section (Miller and Lessard,
2001, p. 437).
The model put forth is divided into four phases – three occurring before or
during the event and one phase after the event – yet all need to be considered
well in advance of the opening. We will further explore the benefit of front-end
management to support this layout, as it is exceptionally crucial and the point at
which many challenges should be addressed. This method requires a heavy
investment in time and information along with experts and knowledge resources,
but can give the entire event a foundation poised to overcome the anticipated –
and the unavoidable surprises – as the opening day draws near.
Assess
In traditional project management studies, knowledge management has only
recently begun to be standardized and regulated as projects are increasing in
22
complexity and size, requiring detailed records of activity. Within the field of
Knowledge Management, there are three distinct characteristics of information:
Explicit: can be collected, classified, described, stored and disseminated
Implicit: experienced based know-how, interpretation residing in the heads
of stakeholders. Requires a process to convert into explicit knowledge and
influenced by how individuals wish to contribute.
Tacit: unique to an individual and situation; intuition based on behaviors
and experiences.
(Adair and Frawley, 2013, p.35)
Even with a push towards standardization, it is suggested that many
workers fall short of fully documenting their knowledge. As one study cites, this is
generally because they do not have the time or resources to comprehensively
document while working on the project (Shokri-Ghasabeh & Chileshe, 2014,
p.127). From this insight it is critical to create an environment early on that is
conducive to knowledge documentation, transfer and implementation (Davenport,
1998, p. 47). And while the direct financial incentives of Knowledge Management
vary from organizations, it’s inarguable that operational improvements and
efficiencies deliver savings in time and resources.
In regards to the Olympics, prior to the 2000 Games in Sydney there were
no standards for collecting or maintaining a central database of information of
“best practices” and strategies used by others (Adair & Frawley, p. 38). Rather
23
the opposite was true where countries would consider their knowledge and
experience proprietary and not wish to share with future hosts until the Olympic
Games Knowledge Service was created. Still, as there have only been, to date,
four rotations of Olympic Games since then, this is a fairly young practice.
David Pitchford, executive direction of the Major Projects Authority, a
management partnership with other governmental departments, suggests that
already some hosts are adopting knowledge transfer by implementing over 300
papers, with more supplied by other vendors, into a central knowledge portal –
the Legacy Learning website. To further support the success of the Games as
well as their commitment to sharing knowledge, Pitchford notes “the London
Olympics were a triumph of project management on a grand scale. Maintaining
the Learning Legacy website forms an important part of our plan to apply the
lessons of this success to other major projects (Olympic Knowledge, 2013).”
While London is following their stated procedure, time will tell how
successful this database of knowledge will be for future hosts. And to further
leverage the immense amounts of information, these new hosts should use this
service as a early as possible and adapt the documentation mindset at the onset.
This will first introduce a much smaller team to the concept and as more workers
are added to the planning and management team, it will become a standard
practice within the organization. Next, an informative handoff of information
should be made from one host to another – it should not merely be a download of
24
information, but a time to offer best practices and further advice on avoiding
challenges to the next host. Finally, the International Olympic Committee should
consider extending this service to become a Center of Excellence so explicit
knowledge might be stored in databases while explicit and tacit knowledge can
reside with experts in the certain areas – specifically relating to the execution of
the Olympics. Though, as Deng and Poon (2011, p. 29) put it, “Although
recurring failures in mega events can find a plausible excuse in a lack of
experience, the forgetfulness, or more precisely the deliberate ignorance of
previous lessons, is the most detrimental risk of all.”
Allocate
After the assessment of the initial vision and stakeholder expectations,
what could be classified as the most critical phase takes place: allocating
resources. Traditionally this is where both mega projects and mega events begin
to derail as it requires the creation of a plan that is appealing, usually at the cost
of gross underestimation.
Or, as Flyvbjerg outlines: ”showing the project at its best … results in an
inverted Darwinism, i.e., the survival of the unfittest (Flyvbjerg, 2008).” Instead of
the best overall project being selected, the project that looks best on paper is
selected. These are typically those with the greatest cost underestimate and
benefit overestimate, resulting in a major benefit shortfall (Flyvbjerg, 2014).
25
The practice of underbidding and overestimating has become so
mainstream that bold claims, such as the one made by Willie Brown regarding
the San Francisco Transbay Terminal construction, reveal the generally
unspoken truth that has plagued mega projects for years:
“News that the Transbay Terminal is something like $300 million over
budget should not come as a shock to anyone. We always knew the initial
estimate was way under the real cost. Just like we never had a real cost
for the [San Francisco] Central Subway or the [San Francisco–Oakland]
Bay Bridge or any other massive construction project. So get off it. In the
world of civic projects, the first budget is really just a down payment. If
people knew the real cost from the start, nothing would ever be approved.
The idea is to get going. Start digging a hole and make it so big, there’s no
alternative to coming up with the money to fill it in.” (Flyvbjerg, 2014).
Similarly, we have seen comparable cost overruns at the most recent
Olympics. The London 2012 Olympics, which were deemed a success, were well
over their original budget estimates (see Table 3) and the Sochi 2014 Olympics
might well forever go down in history as the most expensive – or at least set a
bar no country wishes to surpass.
26
London 2012 Olympic Budget Estimates (in millions £)
2002 2003 2004 2007Operations 779 897 1539 n/aInfrastructure and facilities
403 731 2670 4486
Land acquisition 325 425 - -Site Security - - 190 268Total Security 160.2 170 - 600Tax - - - 836Contingency 109 - - 2747Total cost 1800 3140 4209 9325Source Arup Pricewaterhouse
CoopersLondon 2012 Ltd National Audit
Office
Table 3 (Flyvbjerg, 2014 p. 9).
Traditional project management research is conflicted on the best method
to address these cost overruns and under-allocation. We will consider three
different perspectives: The Hiding Hand Principal, Project Pathogens and
Reference Class Forecasting. Each has it’s a role and impact in the traditional
project management sense and we will further explore if one or a combination of
will will prove more beneficial for mega events.
The first notion is Hirschman’s Hiding Hand which suggests that “the only
way in which we can bring our creative resources fully into play is by misjudging
the nature of the tasks, by presenting it to ourselves in a more routine, simple,
undemanding of genuine creativity than it will turn out to be (Hirschman, 1967, p.
13).” This method acknowledges the reality that many projects cannot fathom
their complexity, so it should be embraced upfront by not trying to anticipate each
challenge. Rather, by starting with a problem one thinks they can solve, human
27
nature has a propensity to believe they can overcome any obstacles encountered
(Hirschman, 1967, p. 14).
The benefit of this method is its underestimations allows projects that
could be perceived as infeasible and too difficult to begin without being turned
down. Hirschman acknowledges the benefit is especially useful on projects that
lack creativity and innovation, specifically industrial projects, where, for instance,
a factory “look[s] as though they could be picked up and dropped anywhere,”
when in reality the unique challenges for each location are usually not uncovered
until the project beings. This can be contrasted against an agricultural project
where it is expected to vary from location to location-based on known differences
(Hirschman, 1967, p. 16-17).
When we consider mega events like the Olympics, we can take a similar
mindset in acknowledging that many of the same venues (e.g.: swimming pools,
tracks, etc) are needed at each event, though, as suggested, the construction of
these each pose unique challenges per location. For instance, the upcoming
2016 Rio Olympic Games will use Guanabara Bay as the venue for sailing and
windsurfing venue, but, as of this writing, and less than a year before their
opening, the lake still remains heavily polluted and recently tested positive for the
deadly KPC enzyme (Kirkpatrick, 2015). This sort of unanticipated complication
is precisely the hidden complication presented by Hirschman. Rio now has the
opportunity to use their creativity and innovation to address the problem, but if
28
they do not meet the deadline they will not only risk the burden of public scrutiny
and disappointment from athletes, but also risk the health and safety of athletes
by allowing them in the water.
Based on Hirschman’s’ recommendations, the Hiding Hand principal is
suited for mega events due to their large industrial needs. But not factored into
this method is a timeline that cannot be moved against a required functionality of
100% -- unlike other infrastructure projects that could be delayed or open in
phases of completion. The implicit deception is useful to the extent of winning a
bid, but the negative ramifications of not being to follow through will be severely
scrutinized by the world, possibly be used as a justification for poor athletic
performance and negatively impact the nation’s Olympic legacy.
Continuing along the notion of hidden problems, Peter Love explores
“project pathogens” that imbed themselves within projects as omission errors,
unnoticed and unseen until an actual problem arises. They are defined as: “slips,
lapses, mistakes, and procedural violations. [Where] active failures are often
difficult to foresee, and therefore, cannot be eliminated by simply reacting to the
event that has occurred.” And often these pathogens enter the system very early
on as seemingly harmless actions, lying dormant until an event spurs it into
fruition (Love, 2009, p. 425).
29
As we look into the points along the project where this occurs, those
interviewed note the upfront design and planning typically experience seemingly
small omissions such as incorrect task sequencing, isolated procedural steps or
a general overload of information where not all details are captured. The authors
attribute these occurrences to process complexity and the pressures
accompanying clients and stakeholders on tight timelines (Love, 2009, p.430)
Project pathogens serve as a cautionary tale for masking problems. While
these errors caused by planning/schedule omission differ from unanticipated or
unacknowledged challenges, the outcomes of heightened expenses and
truncated timelines to address the issues are prevalent. The key distinction
between the two is a pathogen is only seen as a negative while the
underestimation of the Hiding Hand is intended to spur innovation. Regardless,
each carry risks that, if possible, should be avoided by seeking full project
transparency, especially in mega events, so unknowns and mistakes made
upfront do not continue to compound and create a lesser final product.
An alternative method, introduced fairly recently, is Reference Class
Forecasting, deemed by the APA (American Planning Association) as “beneficial
for non-routine projects such as stadiums, museums, exhibit centers, and other
local one-off projects. Planners should never rely solely on civil engineering
technology as a way to generate project forecasts (Flyvbjerg, 2014).” In short,
this method reaches a greater degree of accuracy by benchmarking against
30
actual performance of previous projects where comparable actions are required.
Additionally, the projects need not be of the same type. For instance, when
overhauling city’s public transit system, what could one potentially learn from an
opera house or airport baggage system? Initially all three projects seem vastly
different based on their intended outcomes, but, when viewing the pure statistical
attributes of the project; such as size, throughput or cost overruns, the lessons
can be grouped together to predict the outcome of future projects (Flyvbjerg,
2014).
In general, reference class forecasting for a particular project requires a
curbing of optimistic bias through the following three steps:
(1) Identification of a relevant reference class of past, similar projects. The
class must be broad enough to be statistically meaningful but narrow
enough to be truly comparable with the specific project.
(2) Establishing a probability distribution for the selected reference class. This
requires access to credible, empirical data for a sufficient number of
projects within the reference class to make statistically meaningful
conclusions.
(3) Comparing the specific project with the reference class distribution, in
order to establish the most likely outcome for the specific project.
(Flyvbjerg, 2014)
31
Unlike the Hiding Hand method, Reference Class Forecasting is built on
the foundation of forced honesty by using the past to make decisions about the
future. And given the repository of information and knowledge management
techniques that have been implemented, this method has become easier to
implement. Still, it is not without its flaws – one being its strength: honesty. When
looking back at the cost table of the London Olympics (Table 3), the budget
difference is apparent. If future hosts were to use the real final data to make
estimates, would they stand a chance against winning a bid? Especially if
another is using a method such as Hiding Hand, one is going to appear much
more attractive.
The allocation phase of mega events appears to be the critical point of
successful planning. While it’s still possible to have a successful overall event
like the London games, it’s not arguable that they greatly missed the mark based
on their initial forecast. And with the collection of publically available information,
it’s not feasible for to suggest mega events such as the Olympics can be
accomplished disproportionately cheaper. In addition, the Adapt phase, which we
will discuss next, can benefit from the caution of project pathogens. In these
instances, anticipating there are issues under the surface of the project that have
not been identified can help prepare a mindset to respond if issues should arise.
There is also a detriment to the country or nation when they place
deception upon themselves: Greece is a notable example. It is estimated that the
32
“2004 Olympic Games in Athens, for which cost overruns and incurred debt were
so large they negatively affected the credit rating of the whole nation,
substantially weakening the economy in the years before the 2008 international
financial crisis. This resulted in a double dip— and disaster—for Greece, when
other nations had only a single dip (Flyvbjerg, p.16, 2014).”
When deception and faultily planning goes so far as to bankrupt a nation,
we must consider its usefulness and weigh alternate options. By implementing
techniques like Reference Class Forecasting, mega events cannot hide behind
veiled budgets, but rather can be properly planned for – especially for
nations/cities whose finances cannot reach as deep.
Adapt
Inevitably things will go wrong leading up to the opening ceremony, but
many contingencies in planning a mega event are narrowly focused on a series
of “what ifs.” An alternative perspective moves the planning team away from
adaptation strategies to create a mindset of adaptability to react to these
unanticipated occurrences. Williams and Samset present the notion that a mega
project should begin with multiple “concepts” or strategies to solve the problem
presented. By introducing alternatives and not one dominate, predefined solution,
stakeholders can compare the pros and cons of each, possibly creating a hybrid
solution of concepts. One way to accomplish this is through “soft systems
methodology.” By leveraging this methodology, stakeholders, who have personal
33
subjectivity and success criteria, are able to establish understanding and a
unified vision at the start of the project (Williams & Samset, 2010, p.41). And
while this notion serves well in theory, it’s impossible to know all outcomes.
For an alternate perspective, we will leverage the analogy implemented by
Grabher and Thiel that compares a mega event to disaster preparation. To start,
the immovable deadline of an event’s opening is likened to the imminent landfall
of a Category 5 hurricane playing out in front of a large audience where disaster
support teams have a finite window of opportunity to solve for the “event.” In
addition, the shock – or pure spectacle – experienced by the host city/nation has
a ripple effect felt around the globe. Under these conditions, mere adaption to
foreseeable demands leaves everyone susceptible to those unanticipated
occurrences. “Adaptability requires resources and capacities to generate and to
perform alternative options in changing conditions (Grabher and Thiel, 2014, p.
529).”
Their proposed organizational structure is Heterarchy, which was originally
introduced as a way to describe how the brain is not organized as a distinct
hierarchy, but rather organized so it might re-order values and priorities based on
changing circumstances. Recently, in the field of management, it has been
acknowledged as a way to manage power struggles that arise within large
multinational companies that span the globe. This is done by increasing the
34
interdependencies of networks, creating an interconnected workflow and
decentralizing the core responsibilities for change (Grabher and Thiel, 2014).
Through this method, a “redundancy of difference” is created where the
various groups within an organization critique with varying definitions of
performance criteria. From this comes a reduction in tunnel vision that is often a
result of one hierarchical direction, allowing for adaption of new solutions based
on the collective feedback of the whole network (Grabher and Thiel, 2014, p.
531).
To further the usefulness of the heterarchy approach, examining the London
2012 Olympic games shows a direction that was successful in both the execution
of the games as well as the often overlooked aspect: the Olympic Legacy. The
Olympic Delivery Authority (ODA) setup traditional key performance indicators:
Time
Cost
Quality
Healthy and Safety
Sustainability
Equality and Inclusion
Employment and Skills
Legacy
Design and Accessibility
35
And while traditional project management techniques glorify the use of
performance indicators, the twist was contractors were given the power to decide
how to achieve them. Instead of defining how to achieve success, the project
was largely adaptable thanks to its goal ambiguity. For example, “to be the first
major venue built onsite” could be a motivating objective, but those in Health and
Safety and Legacy had an influence on defining success for that building – not
just those focused on the timeline and cost. Another instance of unrealized goal
ambiguity was a strong push from Sustainability to reuse demolition material – an
example that resulted in both time and cost savings. Which would likely be an
idea that would not have been explored under traditional hierarchy systems
(Grabher and Thiel, 2014, p. 534).
Grabher and Thiel further explore “optioneering” – a leitmotif used to examine
alternatives while being prepared to adapt to the openly accepted, yet unknown,
surprises. This becomes a sort of risk management as well because it prepares
for potential challenges, but more importantly, introduces an adaptive mindset for
all involved in the project rather than pointing blame when a singular solution did
not work. This proved especially beneficial when, in the world financial crisis of
2008 struck. For example, using a cable structure for the Velodrome’s roof was
originally dismissed due to its cost, but after further consideration to the rising
cost of the process of steel and concrete construction, the time saved with cable
would reduce the overall cost (Grabher and Thiel, 2014, p. 535).
36
Aftermath
Each mega event leaves behind unique physical, social and economic
legacies. Positive physical changes include not only the buildings used for the
event, but also the improvements made to transportation, telecommunications
and overall public safety. Socially, the event’s legacy encompasses any
workforce or public training and education, the generation of patriotism and pride
and an increase in the general public’s mood and happiness. Finally, economic
benefits, which can have the most lasting positive impact of them all, include an
increase in income generation, manufacturing and consumer demand during the
event (Junior; 2014).
Yet all of these potential positive aspects of an event’s legacy are tainted
when event organizers and planners do not properly address the previously
discussed challenges. Thus far, the challenges we have illustrated serve as
cautionary tales from mega event history—stories that should serve as warning
signs to future mega events.
Much like the implementation of knowledge transfers, the idea of “legacy”
within the Olympics world is new – not set forth until the IOC charter in 2003, with
an official publication not appearing until 2009. Additionally, since each legacy
criteria is unique to the host and their circumstances, there exists no formal
standard for legacy management. Yet, while this is the most abstract of
management needs, it also is the one that will linger on the mind of the world.
37
Thus far we have explored many of the challenges encountered by a
mega event and leveraged project management techniques to address them.
Still, we have not defined what a successful mega event entails – which becomes
the deepest root of much of their success: what criteria should we measure a
mega event against?
First off, let’s look at a traditional project management example to begin
drawing a comparison: The Sydney Opera House.
“Did people really think that the Sydney Opera House would come in on
budget? Or did we all agree to accept the deception and engage in wishful
thinking in order to make something that we really wanted happen? ... [D]o
Australians really regret those dramatic sails in the harbour? Or would
they have regret- ted more the decision [not to build] that would most
reasonably have been based on a fair prediction of costs?” The logic is
seductive, yet precarious. In retrospect, of course Australians do not
regret the Sydney Opera House, given what it has done for Australia
though, at first, the building was not called “dramatic sails in the harbour,”
but “copulating white turtles” and “something that is crawling out of the
ocean with nothing good in mind” designed by an architect with “lousy
taste.” (Flyvbjerg, 2014, p. 13).
38
The real success of a mega event is its legacy – though, as seen by the
Sydney Opera House example, legacy takes on different views over time and
holds different opinions based on the reviewer. Does one view a stadium as an
engineering marvel or a money drain for taxpayers after the event has concluded
as it must be retrofitted for a new use? Legacy also suffers from the reoccurring
problem of promises, which, at the bidding time, were made in good faith, but the
reality of their implementation often becomes near impossible. Compounding
that, anticipating the economic environment that far into the future is equally
problematic.
Reflecting upon all the challenges faced in managing a mega event,
particularly those of the size and scope of the Olympics, one might wonder if all
the final costs are worth the price. From a pure numbers perspective, no, it is not
– but mega events are so much more than quantifiable number. Or, in the words
of Pierre de Coubertin, founder of the IOC: “Holding an Olympic Games means
evoking history.” So while the 1984 Olympics were profitable, it is unlikely that
their success will ever be replicated using their techniques. We cannot use
expenditures to measure success as the true measures of success are not about
making money – it’s about creating a legacy. Regardless, cost will always be a
factor and with the honest and upfront planning discussed in this paper, mega
events won’t necessarily be cheaper, but they are more likely to not overrun their
budget and, in turn, create new metrics for defining a successful mega event.
39
The mega event isn’t new to the world anymore and with the ever-
increasing expectations pre-existing, it’s a daunting task to manage them. This
paper only addresses the high level challenges encountered by hosts and initial
management recommendations, though the list is by no means exhaustive. The
methods discussed of overcoming these challenges will never be exactly the
same given the unique nature of location, climate, governments and other
influences one might not expect. But these practices, which have been tested in
traditional project management environments, will serve as a foundation to
continue the success and efficiency of this ever-growing industry.
40
Bibliography
Adair, D. & Frawley, S. (2013). Managing the Olympics. Basingstoke: Palgrave
Macmillan.
Arnold, R., & Foxall, A. (2014). Lord of the (Five) Rings. Problems of Post-
Communism, 61(1), 3–12.
Bramwell, B. (n.d.). Strategic planning before and after a mega-event. Tourism
Management, 167-176.
Deng, Y. (2012). Shaping mega‐event flagships: a case study of Expo Center of
Expo 2010 Shanghai, China. Facilities, 30(13/14), 590–610.
Deng, Y., & Poon, S. W. (2013). Meeting sustainability challenges of mega‐event
flagships. Engineering, Construction and Architectural Management, 20(1), 46–
62.
Deng, Y., & Poon, S. (2011). Mega-Challenges for Mega-Event Flagships.
Architectural Engineering and Design Management, 23-37.
Davenport, T., De Long, D., & Beers, M. (1998). Successful Knowledge
Management Projects. http://sloanreview.mit.edu/article/successful-knowledge-
management-projects/
41
Deng, Y., & Poon, S. W. (2014). Positioning mega-event flagships – from
Performing Arts Center of Expo 2010 to Mercedes-Benz Arena. Architectural
Engineering and Design Management, 10(3-4), 233–250.
Flyvbjerg, Bent. "Curbing Optimism Bias And Strategic Misrepresentation In
Planning: Reference Class Forecasting In Practice." European Planning Studies
16.1 (2008): 3-21. Academic Search Complete.
Flyvbjerg, Bent. "What You Should Know About Megaprojects and Why: An
Overview." Project Management Journal (2014): 6-19.
Hirschman, Albert O. "The Principle of the Hiding Hand." Public Interest 0.6
(1967): 10.
Ingraham, Christopher. "The Toll of Human Causalities in Qatar." Washington
Post. The Washington Post, 27 May 2015. Web. 20 July 2015.
<http://www.washingtonpost.com/blogs/wonkblog/wp/2015/05/27/a-body-count-
in-qatar-illustrates-the-consequences-of-fifa-corruption/>.
Juinor, A., & Tur, J. (2014) Mega Sporting Events and Legacy: The Case of the 2014 World Cup.
Kirkpatrick, Nick. "2016 Rio Olympics: Sailing with Sewage." Washington Post.
The Washington Post, 19 Mar. 2015. Web. 20 July 2015.
42
<http://www.washingtonpost.com/news/morning-mix/wp/2015/03/19/the-bay-in-
rio-where-2016-olympic-sailors-will-compete-is-a-disgusting-cesspool/>.
Gauthier, R. (2013). Major event legislation: lessons from London and looking
forward. The International Sports Law Journal, 14(1-2), 58–71.
Giezen, M. (2012). Keeping it simple? A case study into the advantages and
disadvantages of reducing complexity in mega project planning. Jpma, 30(7),
781–790.
Grabher, G., & Thiel, J. (2014). Coping with a Self-Induced Shock: The
Heterarchic Organization of the London Olympic Games 2012. Social Sciences,
3(3), 527–548.
Jennings, W. (2013). Governing the Games: High Politics, Risk and Mega-
events. Political Studies Review, 11(1), 2–14.
Jennings, W., & Lodge, M. (2011). Governing Mega-Events: Tools of Security
Risk Management for the FIFA 2006 World Cup in Germany and London 2012
Olympic Games. Government and Opposition, 46(02), 192–222.
Lessard, D., & Miller, R. (2001). Understanding and Managing Risks in Large
Engineering Projects. International Journal of Project Management, 437–443
43
Love, Peter E. D., David J. Edwards, Zahir Irani, and Derek H. T. Walker.
"Project Pathogens: The Anatomy of Omission Errors in Construction and
Resource Engineering Project." IEEE Transactions on Engineering Management
IEEE Trans. Eng. Manage. (2009): 425-35. Print.
Malfas, M., Houlihan, B., & Theodoraki, E. (2004). Impacts of the Olympic
Games as mega-events. Proceedings of the ICE - Municipal Engineer, 209-220.
McCarthy, William. The Failed Experiment of Vancouver’s 2010 Olympic Village.
(2012). The Failed Experiment of Vancouver’s 2010 Olympic Village, 1–18.
Mega-Challenges for Mega-Event Flagships. (2011). Mega-Challenges for Mega-
Event Flagships, 1–16.
Merwe, A. (1997). Multi-project management—organizational structure and
control. International Journal of Project Management, 15(4), 223-233.
Mills, B. M., & Rosentraub, M. S. (9999). Hosting mega-events: A guide to the
evaluation of development effects in integrated metropolitan regions. Tourism
Management, 34(C), 238–246.
Olympic.org. (n.d.). Retrieved April 9, 2015.
44
Olympic Knowledge. Unleashing a goldmine of Olympics knowledge. (2012,
November 30). The Safety & Health Practitioner, 57-57.
Shokri-Ghasabeh, M., & Chileshe, N. (2014). Knowledge management: Barriers
to capturing lessons learned from Australian construction contractors
perspective. Construction Innovation: Information, Process, Management, 108-
134.
Williams, Terry, and Knut Samset. "Issues In Front-End Decision Making On
Projects." Project Management Journal 41.2 (2010): 38-49. Business Source
Premier. Web. 31 July 2015.