SOUTHWEST NEIGHBORHOOD UPDATE08/25/2014 - 08/29/2014
408 PANAMA MALL
HEADS UP is a construction notification and safety campaign produced by the Stanford University Department of Project Management.
Thank you in advance for your understanding and cooperation.
PARKING STRUCTURE 10
ROBLE GYM RENOVATION
Project Contacts:Sandy Louie, Project Engineer, sjlouie@stanford.eduMark Bonino, Project Manager, mbonino@stanford.edu
Project Contacts:Jasmine McMahon, Project Engineer, jasminemcmahon@stanford.eduMark Bonino, Project Manager, mbonino@stanford.edu
Project Contacts:Jasmine McMahon, Project Engineer, jasminemcmahon@stanford.eduMark Bonino, Project Manager, mbonino@stanford.edu
Work Hours:8am-5pm
Work Hours:8am-5pm
Work Hours:8am-5pm
• Shoring steel delivery will be done early next week.• Wood fence installation along Santa Teresa is on going.• Mobilization of shoring equipment (including large crane) will start next Monday and driving shoring steel will follow.
• Exterior demolition and recycling has been completed.• Clay roofing tile removal continues through 9/19.• Renovation mock-ups are pending.
• Panama will be partially blocked for utility work thru 9/12.• To promote traffic safety, utility work will begin at 6 am.• One way traffic will be enforced along Panama Mall.• Site safety and signage implementation plans are underway.
SOUTHWEST NEIGHBORHOOD UPDATE08/25/2014 - 08/29/2014
HEADS UP is a construction notification and safety campaign produced by the Stanford University Department of Project Management.
Thank you in advance for your understanding and cooperation.
BUILDING 520 RENOVATION
PANAMA MALL IMPROVEMENTS
Project Contacts:Stacey Yuen, Project Engineer, syuen23@stanford.eduKelly Rohlfs, Project Manager, krohlfs@stanford.edu
Project Contacts:Svjetlana Radovic, Project Engineer, sradovic@stanford.eduWayne Kelly, Project Manager, wjkelly@stanford.edu
02-520
WINDHOVER CONTEMPLATIVE CENTER
Project Contacts:Stacey Yuen, Project Engineer, syuen23@stanford.eduMaggie Burgett, Project Manager, burgett@stanford.edu
Work Hours:7am-4pm
Work Hours:6am-3:30pm
Hours:8am-4:30pm
• Preparation of bike rack areas continues on both sides of street.• North side of Lokey Daily Building blocked for path improvements until 8/29.• Construction of crosswalk across Panama Mall. Use caution in area.
• Application of reflecting pool tile and plaster continues.• Interior and exterior touch up and punch list work continue.• Building turnover preparation and systems training continue.
• Roof and interior concrete demolition continues.• Rebar installation at foundations continues.• Core drilling of walls for dowels will begin.• Seismic bracing of existing rafters will begin.